South Korea Built Just 34% of Its Normal Power Line Volume This Year

Korea installed 43 km of transmission lines in H1, 34% of the decade average. No 345-kV or 500-kV HVDC line was completed as resident opposition stalls projects nationwide.

Read
4 min
Words
759
Node
20nm
Operator
Priya Raman

Spec summary

  1. Only 43 km of transmission lines were built in H1, versus a 253.3 km annual average from 2016-2025.
  2. No 345-kV or 500-kV HVDC line was completed in the first half of this year.
  3. Relocating the Dong Seoul converter station would cost at least 1 trillion won and add six years, KEPCO estimated.
  4. About 70% of transmission capacity slated for completion by 2030 has not broken ground, per the National Economic Advisory Council.
  5. A Nov. 17 meeting is the next attempt to break the Dong Seoul impasse after the Nov. 10 session ended without a signed agreement.
Korea Builds Just 34% of Normal Power Lines as Local Opposition Mounts
Fig. AKorea Builds Just 34% of Normal Power Lines as Local Opposition Mounts — minka2507 / pixabay

By Priya Raman

South Korea installed 43 kilometers of new transmission lines in the first half of this year. Annualized, that is 34% of the 253.3-kilometer annual average recorded between 2016 and 2025. The figures come from data KEPCO (Korea Electric Power Corporation) submitted on Nov. 11 to the office of Rep. Lee Jong-bae of the People Power Party, a member of the National Assembly's Climate, Energy, Environment and Labor Committee.

The composition of that figure matters more than its size. Every completed kilometer was 154-kilovolt line. Not one 345-kV line or 500-kV high-voltage direct current (HVDC) line — the core facilities for large-capacity, wide-area transmission — reached completion. A weak year produced only weak infrastructure.

What is driving the delays?

The industry points to local opposition. "These days, the mere rumor that a transmission project is under review is enough to get protest banners hung up," an electrical construction industry official said. "Resident opposition is becoming a constant rather than a variable in transmission construction."

The numbers confirm a slide. According to Lee's office, completions fell from 398 kilometers in 2023 and 328 kilometers in 2024 to 143 kilometers last year. This year has been weaker still. Construction of 22.9-kV distribution networks, which deliver power to end users, has declined for five consecutive years after peaking at 5,327 kilometers in 2021.

"Despite the government's emphasis on timely power supply, results in securing grid capacity have been poor," Lee said. "If infrastructure isn't built on time, the mega-projects the government has touted will amount to nothing more than bounced checks." A KEPCO official responded: "We aim to complete 245 kilometers by the end of this year." The official added that KEPCO will work with relevant agencies to build the grid on schedule. No mechanism for reaching the target was specified.

What is happening at the Dong Seoul converter station?

The Ministry of Climate, Energy and Environment, the office of Rep. Lee Kwang-jae of the Democratic Party — whose constituency includes Hanam — and residents formed a consultative body. It began meeting Aug. 20 and held more than the 16 sessions promised through Oct. 27. It produced a "two-track solution."

The approach pairs two actions:

  • A third-party institution verifies the feasibility of relocating the converter station to Baealmi-dong, Hanam, as residents request.
  • Administrative procedures for construction at the current site proceed simultaneously.

Some residents still refuse to sign. "Some resident representatives demand outright relocation, while others sympathize with the two-track solution but are reluctant to sign the agreement," a consultative-body official said. "Because the representatives' positions vary widely, reconciling the differences is taking longer than expected."

Consensus formed around the two-track solution at a Nov. 3 meeting held past the deadline. Opposition resurfaced at the Nov. 10 session, and the agreement went unsigned. "The process is grueling, but there has been some progress," a government official said. "We hope to find common ground at the Nov. 17 meeting."

Why do experts call relocation unrealistic?

The Baealmi-dong site sits near Paldang Dam, which supplies drinking water to the capital region, and lies in a water-source protection zone with development restrictions. The Dong Seoul site already has security facilities and prepared land; a move would restart ground works from zero.

Costs compound the problem. Relocation would require newly connecting the 500-kV HVDC line and the capital region's distribution networks. When KEPCO reviewed an alternative site near the residents' proposal, it estimated at least 1 trillion won and six additional years.

"Looking for a new site when land has already been secured is inevitably inefficient," said Yoo Seung-hoon, a professor of energy convergence at Seoul National University of Science and Technology. "The delay in building the Dong Seoul converter station has already put a substantial accumulated burden on the east coast grid."

How far does the bottleneck reach?

Industry officials warn that power and water will constrain advanced industries nationwide, not only Hanam. The Honam semiconductor cluster's first-phase transmission plan totals about 23 kilometers, yet observers doubt it can be built on schedule. The 345-kV Singyeryong–Sincheonan line, key to supplying the Yongin semiconductor cluster, lost its site selection committee, which disbanded amid resident opposition.

An analysis by the National Economic Advisory Council found that about 70% of the transmission capacity slated for completion by 2030 has yet to break ground. The government's 245-kilometer pledge for this year now sits against that backlog.

via en.sedaily.com (Source)

Filed under

  • south-korea
  • kepco
  • power-grid
  • hvdc
  • semiconductor-clusters
Share this article:

More from Priya Raman

Priya Raman

Show full bio

Correspondent covering money, funding and market shifts around hardware layer of artificial intelligence at Die Signal.

661 articles

Same lot · LOT-362D

« Previous articleNext article »