Core Scientific files for 285MW data center near Dallas

Core Scientific filed for a 341,325-square-foot data center in Hunt County, targeting 285MW of leasable capacity, an AMD lease and full campus power by 2029.

Read
3 min
Words
572
Node
14nm
Operator
Elena Vasquez

Spec summary

  1. $1.3 billion project; construction scheduled for November 2026 through September 2028.
  2. The filing describes a 341,325 sq ft core-and-shell building at 4852 County Road 3507.
  3. Campus capacity is up to 285MW leasable and 430MW gross, with energization in 2027 and full power in 2029.
  4. AMD is set to lease 110MW; Acciona Energia's nearby Cunningham BESS has 190MW capacity.
  5. Core Scientific acquired 265 Hunt County acres for $232.5 million in March and will exit Bitcoin mining by year-end.
Core Scientific files for 285MW data center outside Dallas, Texas
Fig. ACore Scientific files for 285MW data center outside Dallas, Texas — blickpixel / pixabay

By Elena Vasquez

Core Scientific plans a $1.3 billion data center campus with up to 285MW of leasable capacity about 53 miles northeast of Dallas, Texas. Construction is scheduled from November 2026 through September 2028.

Telios Quinlan One, LLC filed the Core Scientific-Hunt project with the Texas Department of Licensing and Regulation. The filing describes a 341,325-square-foot (31,710-square-meter) data center core-and-shell building at 4852 County Road 3507 in Quinlan, Hunt County.

What will the Hunt County campus contain?

At the time of its March site acquisition, Core Scientific said the campus “could support up to 285MW of leasable capacity (430MW gross capacity) across multiple buildings.” The site could begin energizing in 2027 and reach full power by 2029. An on-site substation is planned.

AMD is set to lease 110MW from Core Scientific in Hunt County under a wider leasing agreement. Acciona Energia’s 190MW Cunningham battery energy storage system sits nearby. The land remains mostly vacant, and the project summary does not establish a direct operating or commercial link between the battery system and data center.

For developers and contractors, the schedule separates three milestones: construction starts in November 2026, initial energization is targeted for 2027, and full power is targeted for 2029. The full-power milestone follows both the construction start and initial energization, rather than arriving with the March site acquisition.

How did Core Scientific acquire the site?

Core Scientific first announced in March that it had acquired a 265-acre site in Hunt County, buying Telios Quinlan One LLC for $232.5 million. The land purchase price is less than one-fifth of the stated $1.3 billion development cost, though the two figures cover different scopes.

Belltown Power, a renewable energy infrastructure developer, previously pursued a project in Quinlan. According to a local anti-data center group, Belltown withdrew its application earlier this year. Its withdrawal preceded the Core Scientific filing, but no further detail was provided on the competing project or the reason for withdrawal.

Why is Bitcoin mining giving way to AI infrastructure?

Founded in 2017, Core Scientific began as a cryptocurrency mining data center operator. It has since pivoted toward AI data center development and now has facilities in Alabama, Georgia, Kentucky, North Carolina, North Dakota, Oklahoma and Texas.

AMD and AI cloud firm CoreWeave are major customers. This week, Core Scientific announced that it “intends to fully exit its Bitcoin mining business by the end of the year,” concentrating the business on AI infrastructure.

What does the filing establish for suppliers?

The Hunt County filing puts a defined building, address and construction window behind Core Scientific’s wider campus plan. Vendors now have four concrete benchmarks: 341,325 square feet of core-and-shell space, a November 2026 start, initial energization in 2027 and full power in 2029.

For power and infrastructure planners, AMD’s 110MW lease provides a named demand anchor inside the campus’s 285MW leasable envelope. CoreWeave remains a major customer, but the announcement does not assign it capacity at this site. The summary also leaves the grid interconnection, substation specifications and construction contractor undisclosed.

The announced mining exit narrows Core Scientific’s stated future focus to AI infrastructure. For counterparties, that shifts the relevant project questions from whether Bitcoin workloads justify new capacity to whether the planned shell, substation and power dates support the company’s data-center expansion.

via datacenterdynamics.com (Source)

Filed under

  • core-scientific
  • amd
  • data-center-construction
  • bitcoin-mining
  • quinlan-texas
Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering people, launches and day-to-day practice in hardware layer of artificial intelligence at Die Signal.

675 articles

Same lot · LOT-362C

« Previous articleNext article »