DC Blox Files for 500,000 sq ft Third Building at Atlanta West Campus

DC Blox files for ATL1-C, a 500,000 sq ft data center in Douglas County, lifting its Atlanta West campus to 200MW and 1.37 million sq ft by December 2029.

Read
2 min
Words
402
Node
7nm
Operator
Marcus Bennett

Spec summary

  1. DC Blox filed for ATL1-C, a 500,000 sq ft (46,450 sqm) data center at 1800 N River Road, Douglasville, Georgia.
  2. Completion is set for December 2029.
  3. Full campus build-out: 200MW across three buildings and 1.37 million sq ft on 100 acres.
  4. Original November 2023 plan was 180MW across 760,000 sq ft on 55 acres with two buildings.
  5. DC Blox's Atlanta East campus in Conyers, started October 2024, will offer 216MW.
DC Blox files for third building at Atlanta West data center campus
Fig. ADC Blox files for third building at Atlanta West data center campus — 12019 / pixabay

DC Blox has filed for a 500,000 sq ft (46,450 sqm) third data center at its Atlanta West campus, pushing the planned site total to 200MW. The project, designated ATL1-C, carries a completion date of December 2029.

The US operator filed a development of regional impact notice with the Georgia state Department of Community Affairs this week. The site sits at 1800 N River Road in Douglasville, Douglas County.

At full build-out, the 100-acre campus in the Douglasville/Lithia Springs area will hold three buildings totaling 1.37 million sq ft (127,277 sqm).

What has changed since 2023?

DC Blox first announced the campus in November 2023. The original plan covered two buildings: the 80MW Building A and the 40MW Building B, plus a substation. At that stage, the campus offered a planned 180MW across 760,000 sq ft (70,605 sqm) on a 55-acre site.

The new filing expands both numbers. The site grows from 55 to 100 acres, capacity rises from 180MW to 200MW, and floor area nearly doubles to 1.37 million sq ft. Reports that a third building was in the works first surfaced in 2024.

The company's website lists the first two buildings as leased. The final 80MW building remains available.

Who is DC Blox?

Bain Capital Credit and Post Road Group back the company. It operates facilities in development or operation across six states:

  • Alabama
  • Georgia
  • South Carolina
  • North Carolina
  • Indiana
  • Tennessee

It also runs cable landing stations in South Carolina and Florida.

What does this change for Atlanta's data center market?

Atlanta gains another large-scale pipeline addition in a metro area already absorbing sustained capacity growth. DC Blox's existing Atlanta facility is small: a 3,350 sq ft (311 sqm) site at 6 West Druid Hills Drive in Brookhaven, with two 1MW generators and 6,470 sq ft (600 sqm) of expansion potential.

The Atlanta West campus multiplies that footprint many times over. Its 200MW planned capacity dwarfs the Brookhaven site's generator-backed load.

The company is also building elsewhere in the metro area. It broke ground on its Atlanta East campus in Conyers, Rockdale County, in October 2024. That site will deliver 216MW of capacity.

Combined, the two campuses put roughly 416MW of planned capacity in DC Blox's Atlanta-area pipeline, anchored by the December 2029 completion target for ATL1-C.

via datacenterdynamics.com (Source)

Filed under

  • dc-blox
  • atlanta-data-centers
  • georgia-data-centers
  • data-center-development
  • douglasville
Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

News editor covering regulation, policy and their impact on hardware layer of artificial intelligence at Die Signal.

681 articles

Same lot · LOT-362E

« Previous article