Riihimäki plan targets 80,000+ sqm; regional pipeline reaches 400 MW

Northern Europe Energy plans at least 80,000 sqm in Riihimäki, while developers advance projects in Lapinlahti and Kauhava; most power and financing terms remain undisclosed.

Read
4 min
Words
890
Node
7nm
Operator
Priya Raman

Spec summary

  1. Northern plans at least 80,000 sqm across 16 hectares in Riihimäki, with completion possible in the 2030s at the earliest.
  2. Riihimäki's city vitality committee approved a preliminary sale-or-lease agreement in September 2026.
  3. Northern's other named developments range from 25 MW in Juva to 400 MW in Jēkabpils.
  4. Ixian's Lapinlahti target is reported at 50 MW, with scope for 150 MW on 13 hectares.
  5. SR-Kiinteistöt's Kauhava lease covers two industrial plots; project specifications remain undisclosed.
Northern Europe Energy targets data center in Riihimäki, Finland
Fig. ANorthern Europe Energy targets data center in Riihimäki, Finland — Leonhard_Niederwimmer / pixabay

By Priya Raman

Northern Europe Energy plans at least 80,000 square metres of data center development on 16 hectares in Riihimäki, Finland, with completion no earlier than the 2030s.

What has Northern agreed in Riihimäki?

Northern Europe Energy Group AS and the City of Riihimäki announced this week that Northern plans to build in the city's northern area, along Hämeenlinnantie. The 16-hectare site called Riihimäenportti VI stands at the junction of Lahdentie and Hämeenlinnantie.

Riihimäki is a city and municipality in southern Finland, 69 kilometres (43 miles) north of Helsinki. The site provides at least 80,000 square metres (861,113 square feet) for data center development.

The announcement identifies a location and development envelope, but supplies no power rating, budget, customer commitments, financing structure, construction schedule or final approval to invest.

Thor Magnus Rovik, CEO of Northern Europe Energy Group AS, said: “Riihimäki is an excellent location for such a data center, and we are very pleased to have signed this agreement with the city.”

He added: “We are grateful for the trust shown by the City of Riihimäki and look forward to developing the project in good cooperation with the city, local industrial partners and the local community.”

What does the preliminary agreement establish?

In September 2026, Riihimäki's city vitality committee approved a preliminary agreement to sell or lease the plot to Northern.

The preliminary agreement enables joint work, but the announcement discloses no land price, lease duration, conditional approvals, construction financing or delivery obligations for the transaction.

Anna-Riitta Kujala, Riihimäki's director of vitality, said: “We are pleased that Northern Europe Energy Group sees potential in Riihimäki as a location for such a significant project. If implemented, the project could open up completely new opportunities for Riihimäki and strengthen our position as an interesting investment destination.”

She added: “The preliminary agreement signed now is just the starting point for joint work. Next, we will find out together what conditions are available for implementing the project in Riihimäki.”

Further conditions remain to be agreed, and the project remains conditional on that process. The claimed municipal benefits remain conditional on implementation. No financial or employment benefit has been quantified.

What is Northern's wider pipeline?

Northern describes itself as a Nordic–Baltic developer of energy and digital infrastructure. Its stated focus includes data centers, battery storage, green hydrogen and Power-to-X projects (converting electricity into fuels or chemicals).

Northern is also developing four data centers with capacities stated in megawatts (MW; one MW equals one million watts):

  • Juva, Finland: 25 MW.
  • Lihula, Estonia: 100 MW.
  • Liepaja, Latvia: 120 MW.
  • Jēkabpils, Latvia: 400 MW.

Only the four named developments carry disclosed megawatt ratings, leaving the proposed Riihimäki site without a comparable measure of electrical scale or project construction timetable.

The Riihimäki proposal therefore has an area target, but no comparable power figure.

Which other Finnish projects are advancing?

In Riihimäki's Haapahuhta area, Data Prop A Oy plans a separate data center. The site contains the protected Haapahuhta spring. The proposal gives no capacity, mitigation plan or construction timetable.

London-based Ixian Infrastructure (Ixian) plans a data center in Varpaisjärvi, within Lapinlahti municipality in central Finland's Northern Savo region. Ixian says it is targeting developments across the Nordics and Europe.

Local press reports a 50 MW target, scope to reach 150 MW and a 13-hectare footprint. These remain reported targets rather than disclosed commissioned capacity or a confirmed final design.

Founder Miles Farlow previously served as vice president of APL's European infrastructure investment team. He worked across APL's data center and renewables platforms.

Swedish energy firm Helios also plans a data center in Lapinlahti's Alapitkä area. Its announcement provides no capacity or construction timetable.

Together, these announcements show active site planning across four Finnish municipalities, although most electrical capacities, capital budgets, and construction timetables remain undisclosed at this stage.

What has SR-Kiinteistöt secured in Kauhava?

The Kauhava City Board recently announced that it had concluded a land lease agreement with SR-Kiinteistöt Oy for two industrial plots in the Riihimäki area of Kauhava. The lease enables the tenant to carry out reports on planning, development and construction for a proposed data center.

The lease agreement enables reports on two plots, but gives no floor area, electrical capacity, budget, contractor, customer or committed start date for the proposal.

Here, Riihimäki denotes an area within Kauhava, not the larger municipality north of Helsinki.

Kauhava is a town and municipality in western Finland's South Ostrobothnia region, 400 kilometres (250 miles) northwest of Helsinki.

SR-Kiinteistöt is a private real estate company offering office, warehouse and production premises in the Pori region. It reportedly has several Finnish data center projects in preparation, including Kuusamo and Laihia.

What can the market conclude?

For developers and investors, the present evidence supports a pipeline assessment, not a forecast of operating Finnish data center capacity or a firm construction timetable.

The Riihimäki project has no stated MW rating. Local press attributes Ixian's 50 MW figure to the company.

The immediate market signal is land control and early planning across multiple Finnish municipalities. It does not establish how much power will be commissioned, when construction will start, or who will finance each project.

Area targets, power ratings, project approval and commissioned capacity remain separate milestones.

via datacenterdynamics.com (Source)

Filed under

  • data-center-development
  • finland
  • nordic-region
  • riihimaki
  • megawatt-capacity
Share this article:

More from Priya Raman

Priya Raman

Show full bio

Correspondent covering money, funding and market shifts around hardware layer of artificial intelligence at Die Signal.

661 articles

Same lot · LOT-362D

« Previous articleNext article »