PDG, Stockland file Sydney data-center projects up to 365MW
PDG and Stockland have filed for Sydney data centers totaling up to 365MW, with Stockland outlining AU$7.24 billion of investment and a 55MW Q1 2029 start.
- Read
- 3 min
- Words
- 698
- Segment
- AI Datacenter Infrastructure
- Operator
- Amara Osei
Spec summary
- PDG plans a 100MW first Australian campus on 12.7 hectares at 192 Narellan Road, Campbelltown.
- Stockland expects 55MW online at Wetherill Park in Q1 2029 and 250MW of grid capacity by Q1 2031.
- Project Blue Tongue at 3 Davis Road would provide 88MW across two three-story data-center buildings.
- Stockland’s revised Kemps Creek filing seeks 365MW of IT capacity across 86,355 sqm on 20 hectares.
- Planned investment is AU$2.25 billion for Wetherill Park and AU$4.99 billion for Kemps Creek.

Stockland’s two Sydney data-center filings call for AU$7.24 billion in investment, while Princeton Digital Group seeks approval for its first Australian campus, with 100MW planned in Campbelltown. The filings cover planned capacity in Campbelltown, Wetherill Park and Kemps Creek, plus a separate 88MW development next door to Stockland’s Wetherill Park site.
What does the Campbelltown filing cover?
PDG filed a SEARS application with the New South Wales government for the 192 Narellan Road Data Center. The 12.7-hectare site sits within the Maryfields Estate, about 44km southwest of Sydney’s central business district, on undeveloped land.
Codenamed Project Genesis, the 100MW campus would contain two buildings: a two-story facility and a three-story building. PDG also plans an on-site substation, rooftop solar panels and a battery energy storage system.
Documents indicate that PDG works with Sydney-based Morehuman Property Group, which traditionally focuses on residential and hotel developments. In 2020, the Franciscan Order of Friars Minor sold the site to Uniting Care for about AU$18.5m.
The land previously carried plans for a senior-living development with 500 dwellings and 200 aged-care beds, part of the wider Maryfields Estate scheme, which included a business park. The data-center filing would establish PDG’s first Australian campus at 100MW, with on-site solar and battery storage included.
How large is Stockland’s Wetherill Park proposal?
Stockland filed a SEARS application for the Wetherill Park Data Center at 2 Davis Road, in the Wetherill Park area of North Sydney, about 25km west of the Sydney CBD. The project comprises a four-story, 38,090 sqm (409,997 sq ft) building and an on-site substation.
The 170MW building would contain 20 data halls, use a closed-loop cooling system to reduce water consumption and include air-cooled chillers. Stockland expects the first 55MW to come online in Q1 2029 and plans to ramp grid capacity to 250MW by Q1 2031.
Stockland will demolish the warehouse and distribution facility built on the Wetherill Park site in the 1980s. Holroyd Terminal Station stands about 700m northeast. The company plans AU$2.25 billion of investment in the project.
At 3 Davis Road, Stockland’s Davis Road Data Center, or “Project Blue Tongue,” would provide 88MW through two three-story data-center buildings, a two-story tape-storage building and an on-site substation. The two adjacent Wetherill Park projects list 170MW and 88MW of building capacity.
What changed at Kemps Creek?
Stockland and Fife Capital first filed in April for a single 168MW building at 90 Aldington Road in Kemps Creek, with 14 data halls and a planned 1GW substation.
Stockland’s updated SEARS application seeks two multi-story buildings on 20 hectares at 74–88 Aldington Road. The pair would provide 365MW of IT capacity across 86,355 sqm (929,517 sq ft) and include the 1GW substation known as the Ropes Creek switching station.
“Since the issue of the previous SEARs for 90 Aldington Road in April 2026, the proposal has evolved substantially through the consolidation of Lots 43 and 90, refinement of the infrastructure strategy, and continued engagement with key agencies and infrastructure providers,” Stockland said in its filing.
The updated proposal calls for AU$4.99 billion, or US$3.35 billion, in investment. The revision more than doubles proposed IT capacity and shifts the Kemps Creek plan from one building to two.
Who is behind the filings?
PDG, an Asia-Pacific data-center firm founded in 2017, has data centers in operation or development across China, Singapore, India, Indonesia, South Korea, Malaysia and Japan. The company says its portfolio totals 1.8GW.
Founded in 1952, Sydney-based Stockland is one of Australia’s largest property groups. The company has recently focused more on data centers and partnered with EdgeConneX. It operates a data center in Sydney’s Macquarie Park area, plans further expansion there and has several developments under way around Melbourne.
Stockland has also recently backed off from a planned project in Sydney’s Cooks River area. The filings expand Sydney’s development pipeline, but only Wetherill Park carries a stated commissioning schedule.
via datacenterdynamics.com (Source)
More from Amara Osei
Show full bio
Staff writer covering money, funding and market shifts around hardware layer of artificial intelligence at Die Signal.
793 articles
Same lot
- Macquarie Files for 200MW Sydney Campus in AU$2bn Push
- CDC plans 1.4GW, AU$15bn data center campus near Wagga Wagga
- CDC quadruples Kemps Creek plan to 1.4GW in single filing
- Quantum DC Proposes 1.2GW Data Center and Power Campus Near Adelaide
- Two Sydney data centers scrapped, 1.2GW Tungkillo project paused