Merlin pauses 48MW Bilbao data center work over power

Merlin has paused the 48MW Arasur 4 and 5 projects in Álava after power delays. An €863m, mostly battery-storage contingency and possible relocations frame the €1.6bn risk.

Read
3 min
Words
565
Segment
AI Datacenter Infrastructure
Operator
Elena Vasquez

Spec summary

  1. Merlin paused work on the 48MW Arasur 4 and 5 projects in Álava over electricity supply.
  2. One 24MW Arasur building is live; the first building was set to start at 2MW against a 100MW IT design.
  3. Merlin estimates a royal decree could require €863 million more, mainly for battery energy storage.
  4. The additional investment equals 11.3% of planned spending, with about 35% expected to be recovered.
  5. Merlin entered data centers in 2021 and has since raised more than $1 billion.
Merlin pauses development on two data centers near Bilbao, Spain, due to grid issues
Merlin pauses development on two data centers near Bilbao, Spain, due to grid issues — analogicus / pixabay

Merlin Properties has paused work on the Arasur 4 and Arasur 5 data centers in Álava, putting 48MW of planned Bilbao-area capacity on hold over electricity supply. The move affects the next two buildings in Merlin’s Arasur development; a separate 24MW building remains live.

CEO Ismael Clemente confirmed: “The company will not proceed with these developments until it has sufficient guarantees of electricity supply.” Solaria, one of Merlin’s energy partners in the region, was due to provide part of both facilities’ electricity through renewable generation. Administrative issues affecting several of Solaria’s solar projects have compromised part of that planned supply.

The Basque Government’s refusal to authorize several planned solar farms has thrown the supply schedule into question. Merlin and Solaria are now exploring whether to shift the data centers’ energy consumption to other areas of Spain with greater self-consumption capacity.

What changes at Arasur?

One 24MW building is already live at Arasur. A second is due live before the end of the year, and a third is due next year; the latter two facilities total 48MW.

The first building can accommodate up to 100MW of IT capacity, but it would initially operate at just 2MW. Current electricity supply limits therefore determine its starting load, regardless of the building’s larger technical design.

What would the new rules cost?

Spain’s government first proposed its data-center regulatory framework in late August, and Spain DC plus individual companies remain skeptical. Merlin has prepared a contingency should a royal decree take effect, with an estimated €863 million needed to adapt its facilities.

Most of that spending would go into battery energy storage systems. The estimate adds 11.3% to investments already included in Merlin’s plans, while the company expects to recoup approximately 35% of the extra cost.

Merlin frames the contingency around adapting its facilities, rather than only protecting the paused Arasur projects. That scope matters as the company balances operating capacity, future development and regulatory requirements across several sites.

How can Merlin protect the €1.6bn pipeline?

Merlin is considering shifting part of its development capacity to Portugal and Madrid, and adding a second project in Aragón. CEO Ismael Clemente warned that projected energy conditions could jeopardize full development of the €1.6 billion ($1.67 billion) project.

The company is working to safeguard the project’s viability and anticipate the new regulations’ effects. It is also weighing battery storage and location changes against the continuing need for guaranteed electricity at Arasur.

Who is behind the portfolio?

The major real-estate company first announced its move into data centers in 2021, partnering with Edged, then the new venture from Aligned founder Jakob Carnemark. Merlin has since raised more than $1 billion for further data-center development.

Merlin’s development program spans Spain and Portugal:

  • Spain: Bilbao, Arasur, Madrid-Getafe and Barcelona.
  • Portugal: Lisbon.
  • Customers: Nebius is confirmed; Meta is rumored.

Merlin previously backed off a planned campus in Andalusia because of energy issues. The Arasur pause extends that constraint into a portfolio with one operating building, two suspended buildings and a first structure designed for 100MW of IT load.

The immediate tests are the Basque authorizations for Solaria’s solar farms, the terms of the pending decree and the allocation of future capacity. Together, they sit behind the €863 million contingency and the wider €1.6 billion development plan.

via datacenterdynamics.com (Source)

Filed under

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering people, launches and day-to-day practice in hardware layer of artificial intelligence at Die Signal.

770 articles

Same lot

« Previous articleNext article »