FERC Rejects Most PJM Large-Load Rules, Keeps Registry

FERC rejected most of PJM's large-load framework in October 2026, approving only a registry. Curtailment died, states gained a say, and builders still lack a full rulebook.

Read
4 min
Words
781
Node
5nm
Operator
Grace Kim

Spec summary

  1. FERC rejected most of PJM's large-load framework in October 2026
  2. One piece survived: FERC approved a large-load registry for PJM
  3. FERC said states must help decide which retail customers can be curtailed
  4. A Forbes-reported 50 MW / March 2027 threshold remains unconfirmed
  5. McKinsey: data centers could reach 15% of U.S. electricity demand by 2030
PJM: FERC Rejects Most Large-Load Rules, Keeps 1 Registry
Fig. APJM: FERC Rejects Most Large-Load Rules, Keeps 1 Registry — AI-generated

In October 2026, the Federal Energy Regulatory Commission rejected most of PJM's proposed framework for connecting and managing large loads — and approved exactly one piece of it, a large-load registry. The result: the largest U.S. power grid now runs on half a rulebook, and data center builders are asking regulators for terms they can actually plan around, according to a Reuters report.

Three facts anchor the story. FERC rejected the bulk of PJM's framework, including a mechanism for temporary curtailment (short, ordered reductions in consumption) of large loads during grid strain. FERC approved a large-load registry for PJM. And the commission said states must take part in deciding which retail customers can be curtailed.

What did FERC actually reject?

The most visible casualty was curtailment. PJM had proposed that a big data center could be told to cut its draw when the grid was tight. FERC turned that down as written.

That matters commercially. An AI training cluster that can be paused carries a different risk profile than one that cannot. Operators sell reliability, and any rule letting a grid operator switch them off — even briefly — changes contract pricing, backup-generation sizing and customer negotiations. The rejection removes that specific risk for now, but the reliability concern behind the proposal hasn't gone anywhere.

Why the registry is the one win

A registry gives PJM a structured list of large customers planning to connect, with information on when they expect to ramp up. Michael Daschle, energy procurement lead at Rowan Digital Infrastructure, told Reuters the registry would improve grid planning and capacity-ramp forecasts.

Grid planners work from forecasts. A developer filing interconnection requests at five sites but building one distorts demand fivefold; a fast build the operator never hears about shows none. The registry fixes both errors by creating a single place where large-load plans are recorded.

It doesn't settle who pays for upgrades, who connects first, or what happens in a shortage. Those questions lived in the rejected portions.

What does this change for state regulators?

Plenty. FERC said states must help decide which retail customers can be curtailed. The commission regulates wholesale markets and transmission; states regulate retail service, the utility-customer relationship. Curtailing a data center served by a local utility touches both. How states will participate isn't detailed in the reporting — a state-approved priority list, an opt-in structure, or a menu of options all remain open.

That creates a coordination challenge across PJM's many states. Some have courted data centers with tax incentives; others question the burden on residential ratepayers. State approaches have diverged quickly, and any revived curtailment rule will likely include a state sign-off step.

The unconfirmed 50 MW claim

One circulating detail deserves a warning label. A separate Forbes report describes a requirement that data centers above 50 megawatts secure dedicated new power by March 2027. That claim does not appear in the Reuters story, and it could not be confirmed that final rules require it. Treat both figures as unverified until PJM's revised filing or FERC's accepted language states them directly.

Market impact

Developers with sites already in motion benefit most from the registry, which formalizes their place in line. Developers still choosing regions may weigh PJM's uncertainty against other grids. Hyperscalers have structural reasons to stay — fiber routes, customer proximity, industrial infrastructure — so the rules question changes cost and timing, not interest. If curtailment terms stay vague, expect more projects to pursue on-site or co-located generation, a trend already visible in other regions.

The context is scale. The McKinsey Global Institute's 2025 energy-transition review wrote that "Data centers could account for as much as 15 percent of U.S. electricity demand by 2030."

What happens next

Reuters gives no dates for the next filing or a final decision. Likely moves, based on the confirmed record: PJM returns with a narrower proposal built around the approved registry; curtailment comes back with state sign-off built in; voluntary flexibility — agreeing to reduce load in exchange for faster connection — grows as a competitive edge.

Practical steps for developers while rules settle:

  • Register projects accurately in the large-load registry
  • Engage the local utility early; it sits between developers, PJM and states
  • Track state regulators' curtailment positions
  • Model a curtailment scenario in the business case
  • Evaluate on-site or co-located power options
  • Verify any numeric threshold against primary filings, not summaries

The bottom line: FERC handed builders a registry and took away a curtailment tool. Until PJM files revised language and FERC rules on it, planning in the region carries more risk than builders want.

via shattered.io (Source)

Filed under

  • pjm
  • ferc
  • large-load-registry
  • data-center-interconnection
  • load-curtailment
Share this article:

More from Grace Kim

Grace Kim

Show full bio

Market editor covering regulation, policy and their impact on hardware layer of artificial intelligence at Die Signal.

665 articles

Same lot · LOT-362E

« Previous articleNext article »