Test report · tested November 16, 2026
AI Datacenter InfrastructureDevice under test
Equinix files $500 million Dallas data center for 2029
Equinix filed for a $500 million, 372,445-square-foot Dallas data center, part of a three-project pipeline near Love Field with schedules extending from 2026 to 2029.
- Read
- 3 min
- Words
- 584
- Segment
- AI Datacenter Infrastructure
- Operator
- Grace Kim
Spec summary
- Equinix's DA13-1 filing covers a $500 million, four-story, 372,445-square-foot Dallas data center.
- DA13-1 construction is scheduled from February 2027 through December 2029.
- DA12-1 calls for $542.8 million in investment and 372,515 square feet of floor area.
- DA12-2 calls for $293.7 million in investment and construction from September 2027 to March 2028.
- Equinix currently lists eight Dallas-area data centers and one facility in Houston.

Grace Kim
Equinix plans a $500 million, 372,445-square-foot data center in Dallas, with construction scheduled from February 2027 through December 2029.
DA12 LLC (limited liability company), an Equinix affiliate, filed with the Texas Department of Licensing and Regulation (TDLR) for DA13-1, its new data center project at 1520 West Mockingbird Lane in Dallas, Dallas County.
The application describes a four-story building on a vacant industrial parcel near Love Field Airport. The filing places the $500 million project's construction across a nearly three-year window, running from February 2027 to December 2029.
What does this change for Equinix’s Dallas footprint?
Equinix currently lists eight data centers around the Dallas area. The company also has one facility elsewhere in Texas, in Houston. DA13-1 would put another Dallas-area location into Equinix's development schedule, next to the DA12-1 and DA12-2 projects it filed for at a separate Mockingbird Lane address.
For operators and site-selection teams, the practical change is a longer, staggered construction pipeline around Love Field, not an immediate increase in operating capacity. The filing sets out planned work at two addresses across the street: DA12-1 from February 2026 to October 2027, DA12-2 from September 2027 to March 2028, and DA13-1 from February 2027 to December 2029.
The schedules overlap for much of 2027 and 2028. DA13-1 begins before DA12-2 and remains under construction after the neighboring project reaches its scheduled March 2028 construction end. The cited schedules do not provide an in-service date.
At 1520 West Mockingbird Lane, the land previously hosted Mockingbird Office Park, an office complex dating to the 1970s that stood until its demolition around 2022. The property was formerly known as Oakbrook Plaza. 2GR Equity and Legacy Capital acquired the site in 2016, and Center Court Partners acquired it in 2019.
DA12 LLC shares its listed address with Equinix. The LLC also names Arquelle Shaw, the company's America’s president, as its listed contact.
Equinix filed for DA12-1 and DA12-2 in November 2025. The applications cover 1550 West Mockingbird Lane, directly across the street from DA13-1. The parcel previously housed Taylor Publishing Company and Balfour Publishing; the building has been demolished.
- DA12-1: Equinix aims to invest $542.8 million in a four-story, 372,515-square-foot facility, equivalent to 34,610 square metres (sqm). Scheduled work runs from February 2026 through October 2027.
- DA12-2: Equinix plans to invest $293.7 million in a second four-story building at the same address. Scheduled work runs from September 2027 through March 2028.
The November filings establish the first two construction windows. DA12-1 is due to start in February 2026 and finish in October 2027; DA12-2 follows with a September 2027 start and a March 2028 construction end. DA13-1 is scheduled to start in February 2027 and extends the Dallas construction schedule to December 2029.
For Equinix, that creates three identified projects on two adjacent parcels, with two simultaneous schedules beginning in February 2027 and activity at both addresses through March 2028. The filings cover redevelopment of two former publishing or office sites near Love Field Airport.
Among the three proposals, DA12-1 carries the highest stated investment at $542.8 million, ahead of DA13-1 at $500 million and DA12-2 at $293.7 million. DA13-1 has the longest stated construction window, while DA12-1 and DA12-2 are scheduled to end construction first.
via datacenterdynamics.com (Source)
More from Grace Kim
Show full bio
Market editor covering regulation, policy and their impact on hardware layer of artificial intelligence at Die Signal.
764 articles
Same lot
- Equinix opens SG6 in Singapore with $290m initial investment
- AWS Files Plans for 36-Building Data Center Campus in Pennsylvania
- $8bn, 756MW data center filed in Quanah, near Iren-Crusoe site
- Core Scientific files for 285MW data center near Dallas
- Harwood rejects data-center restrictions as other US votes fail