EdgeCore opens 216MW Reno campus first hall, tops out second

EdgeCore opened RN01 and topped out RN02 at its 56-acre Reno campus, targeting 216MW across three buildings and nearly 1 million sq ft, five years after first planning the site.

Read
2 min
Words
471
Segment
AI Datacenter Infrastructure
Operator
Priya Raman

Spec summary

  1. Reno campus targets 216MW of IT capacity across three buildings at full build-out
  2. RN01 opened and RN02 topped out on the same day this week
  3. Ground broke in August 2023; planning dates back to 2018
  4. Partners Group acquired EdgeCore in 2022 with up to $1.2 billion for build-outs
  5. Site spans 56 acres and nearly 1 million sq ft (92,905 sqm)
EdgeCore launches Reno data center, tops out second building on campus
EdgeCore launches Reno data center, tops out second building on campus — AI-generated

EdgeCore Digital Infrastructure cut the ribbon on its first Reno data center and topped out a second building on the same day this week, moving the Nevada campus toward a planned 216MW of IT capacity.

The company confirmed both milestones in a LinkedIn post. "Yesterday, we celebrated the ribbon-cutting of our RN01 data center and the topping out of RN02 at our Reno Industrial Center campus," EdgeCore wrote. "Achieving both milestones on the same day underscores EdgeCore's continued momentum and ability to deliver data center capacity with certainty."

The claim of delivery "with certainty" deserves scrutiny. The project took roughly five years to reach this point from first planning, though construction itself moved quickly.

What does the campus actually deliver?

The numbers are concrete. At full build-out, the 56-acre Reno campus will total 216MW of IT capacity (the power available to run customer servers, excluding cooling and overhead) across three buildings and nearly 1 million sq ft, or 92,905 sqm.

EdgeCore broke ground on the site in August 2023. Company planning for a Reno project dates back to 2018, meaning five years elapsed between initial intent and first operational capacity. The company did not disclose how much of the 216MW RN01 brings online today, how much capacity is pre-leased, or the expected completion date for RN02.

The site sits inside the Tahoe-Reno Industrial Center. It uses a closed-loop cooling system, a design that recirculates coolant rather than drawing continuously on municipal water, to reduce water use. EdgeCore did not quantify the expected water savings.

Who is behind the build-out?

Launched in 2018, EdgeCore was acquired by Swiss private equity firm Partners Group in 2022. The acquisition came with plans to invest up to $1.2 billion to fund the purchase and the build-out of existing and future data center sites.

Since then, the company has expanded rapidly. It currently operates facilities, or has them under development, in:

  • Silicon Valley, California
  • Phoenix, Arizona
  • Reno, Nevada
  • Multiple sites in Virginia

The company did not disclose total operating capacity across those markets, lease rates, or specific customers at any location.

What remains unanswered?

The same-day milestone framing emphasizes speed, but the record shows a slower arc from concept to concrete. Planning began in 2018; ground broke in August 2023; the first building is now live. The second building has reached topping out (the point at which the final structural element is placed), which typically precedes mechanical fit-out by many months.

Reno has become a secondary data center market for operators seeking cheaper power and land than Silicon Valley offers, and EdgeCore's 216MW positions it among the larger projects in the region. Whether demand absorbs that capacity, and on what timeline, remains the open question the company's statements do not address.

via datacenterdynamics.com (Source)

Filed under

  • edgecore
  • reno-data-center
  • 216mw-campus
  • nevada
  • data-center-construction
Share this article:

More from Priya Raman

Priya Raman

Show full bio

Correspondent covering money, funding and market shifts around hardware layer of artificial intelligence at Die Signal.

731 articles

Same lot

« Previous articleNext article »