Texas Restarts Data Center Permit Reviews, Clearing SpaceX's $24B Starbase Project

Texas has restarted air-permit reviews for data centers, granting one for gas generation feeding SpaceX's $24B Starbase project — a month before a governor-elect who wants a freeze takes office.

Read
3 min
Words
608
Segment
AI Datacenter Infrastructure
Operator
Elena Vasquez
Texas Resumes SpaceX Data Center Review With a Month Left in Governor's Term
Texas Resumes SpaceX Data Center Review With a Month Left in Governor's Term — blickpixel / pixabay

Texas has resumed environmental permit reviews for data centers, ending a suspension that ran through the midterm elections — and it did so with roughly a month left in Republican Governor Greg Abbott's term. Reuters reported on the 18th that the Texas Commission on Environmental Quality (TCEQ) had restarted its review of air emissions permits tied to data center projects.

The timing matters for practitioners. Politico reported earlier that on the 16th the TCEQ granted an air emissions permit for natural gas power generation facilities feeding a data center SpaceX is building at Starbase in southern Texas. Initial investment in the combined data center and power plant is estimated at about $24 billion.

The TCEQ kept its statement procedural. The agency said it had "resumed normal permitting review procedures and will review applications in accordance with all applicable state and federal laws and regulations."

Why had reviews stopped in the first place?

Governor Abbott halted new grid connections for data centers in August, roughly three months before the midterms, and ordered an investigation into their electricity and water use. The trigger was mounting resident opposition — specifically complaints that power-hungry data centers were pushing up household electricity bills.

The state carries outsized weight here. Texas accounts for about one-quarter of new data center projects planned or under way in the United States. Regulations on data center construction have also been introduced in many other states.

What does the resumption actually change?

Not as much as the headline suggests. The Texas Tribune, a local news outlet, reports that a separate review by the state's power regulator remains on top of the TCEQ process. Final findings from that review are projected to land next month.

So an air permit is one gate, not the whole corridor. Projects like Starbase still depend on the power regulator's conclusions before they can move at full speed.

What comes in January?

Governor-elect Gina Hinojosa, a Democrat who won the midterm, has said new data center construction and permitting in Texas should be suspended immediately until laws protecting residents are in place. In a CNN interview on the 5th, shortly after the election, she stressed that protective legislation should come first.

Her position isn't blanket opposition, though. Hinojosa has said she doesn't dislike data centers themselves — she objects to how they shift costs onto local communities.

That distinction could define the next two years of Texas permitting. A governor who wants a statutory framework, not a ban, leaves room for negotiation over water rights, grid fees and local compensation.

Can states actually block these projects?

Some observers doubt it. Jimmy Lee, chairman of industrial AI company ASI Foundry and a former Virginia deputy secretary of commerce, argues residents oppose data centers because well-funded companies lobby and build without their knowledge.

"State governments and companies write contracts among themselves and build data centers as they please, so residents are left out," Lee said. Virginia is currently the largest data center hub in the United States.

Lee points to a working model instead of a blockade. "Going forward, it will become important to build systems so that residents near data centers can share in the benefits of construction," he said, citing Loudoun County, Virginia. There, increased tax revenue from data centers is used to lower property tax burdens for residents.

For developers and local officials in Texas, the read is straightforward: the permitting machine is running again, but the political ground under it shifts in January. Anyone with a project in the TCEQ queue has a narrow window before a governor takes office who wants to pause the queue entirely.

via en.sedaily.com (Source)

Filed under

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering people, launches and day-to-day practice in hardware layer of artificial intelligence at Die Signal.

770 articles

Same lot

« Previous articleNext article »