Test report · tested November 25, 2026
AI Datacenter InfrastructureDevice under test
OU Study of 212 Data Centers Names Land-Use Diversity as Top Siting Factor
University of Oklahoma researchers examined 212 U.S. data centers run by 11 tech firms and found land-use diversity, not cheap acreage, was the strongest predictor of siting. Kijin Seong co-authored the study, published November 20, 2026.
- Read
- 6 min
- Words
- 1,153
- Segment
- AI Datacenter Infrastructure
- Operator
- Amara Osei
Spec summary
- Researchers at the University of Oklahoma examined 212 U.S. data centers operated by 11 major technology companies, including Amazon, Microsoft, Google and Meta.
- Land-use diversity was the strongest siting factor, ahead of electrical substations, major roads and IT worker concentrations.
- Kijin Seong, Ph.D., assistant professor at OU's Gibbs College of Architecture, co-authored the research; the announcement is dated November 20, 2026, updated November 22, 2026.
- The study reports associations, not causation, and provides no investment, jobs, tax, water or electricity figures.
- Site selector Chris Lloyd of McGuireWoods Consulting stated: 'Power is king.'

University of Oklahoma researchers examined 212 U.S. data centers operated by 11 major technology companies — Amazon, Microsoft, Google and Meta among them — and found that land-use diversity was the strongest factor explaining where those facilities landed. The university published the announcement on November 20, 2026, and updated it on November 22, 2026.
The result runs against the common assumption that operators hunt for wide-open, single-purpose land. The OU team found the reverse pattern holds in the data: districts mixing housing, commerce, industry and services tracked most closely with the 212 observed locations.
What Did the Study Actually Measure?
Kijin Seong, Ph.D., an assistant professor in the Division of Planning, Landscape Architecture and Design at OU's Christopher C. Gibbs College of Architecture, co-authored the research. The team did not survey executives. It worked backward from where existing facilities sit and tested which local characteristics tracked with those locations.
The published material names only four of the 11 operators and does not identify the co-authors. It reports aggregate findings, so company-level patterns — whether Meta favors different communities than Microsoft, for instance — remain unpublished.
The analysis grouped explanatory factors into three families:
- Land use: the mix of activities in the surrounding area
- Infrastructure: electrical substations and major roads
- Workforce: concentrations of information technology workers
The study reports associations, not causation. A substation or a mixed-use neighborhood may accompany a siting decision; the announcement does not claim either one caused it.
Why Does Land-Use Diversity Lead the List?
Diversity describes the surrounding district, not the parcel itself. A facility can sit on a quiet lot and still score high if the area around it mixes uses. For local officials, that distinction changes the pitch: a town does not need to rezone everything for servers, it needs to look like a place where varied development already happens.
The study summary offers no causal story, and none should be invented. Mixed-use areas tend to carry what a large facility needs to function — established utility service, road networks, nearby workers and permitting offices accustomed to different building types. Diversity may work as a proxy for all of that.
Practitioner checklists, such as site selection criteria guides from firms like Base Operations, have long treated land as a screening gate. The OU analysis adds what those checklists rarely supply: a pattern drawn from where 212 real facilities actually went.
What Role Did Substations, Roads and Workers Play?
Three supporting factors added explanatory power, none stronger than land-use diversity:
- Electrical substations: A data hall is a large electrical load with cooling attached. Sitting near a substation shortens the path from grid to racks. The study reports no megawatt figures.
- Major roads: Construction crews, generators, cooling equipment and replacement hardware all arrive by truck, and roads bring staff to shifts.
- IT worker concentrations: Facilities cluster where technology workers already live, suggesting talent shapes the map as much as land and power.
The workforce finding carries the sharpest implication for smaller communities. Courtland Robinson, a director at Brasfield and Gorrie, told a SEDC site-selector discussion: "For a rural community, the workforce is a big consideration." He described the developers' workaround: "You can import a certain amount of labor to a new facility where a workforce for those data center occupations didn't exist."
That comment complicates the OU result usefully. A thin local talent pool may not block a project; it may raise the cost and slow the ramp.
What Do Industry Voices Say?
Seong framed the physical basics plainly in an interview with okcfox.com: "The buildings that hold data centers need land, a lot of electricity, water for cooling and fiber connections." Note that water and fiber appear in that quote but not among the study's tested factors; treat them as background requirements Seong described, not measured results.
Chris Lloyd, senior vice president and director of infrastructure and economic development at McGuireWoods Consulting, compressed the industry view into three words in the SEDC discussion: "Power is king." That sits comfortably beside the OU substation finding.
In the university's words: "Our study serves as a starting point for communities preparing for the physical demands of the AI boom."
What Does the Study Not Say?
The published material provides no investment amount, job count, tax incentive, water-use figure, electricity requirement or construction date. It carries no quoted statement from any company or community official. Anyone citing those details alongside the study is importing them from elsewhere. The announcement describes factors that "helped explain" locations — association, not proof.
Who Gains From a Clearer Siting Map?
When a community can point to published evidence about what operators look for, it can prepare before a developer arrives. When developers hold the same evidence, they can target towns that already fit the profile. Mid-sized towns with mixed land use and decent grid access emerge as potential winners under the OU framing. Remote areas selling only cheap acreage may find the study cuts against their pitch.
For local planners, the immediate moves are measurable from public data: map land-use mix across districts, inventory substations and spare capacity, check truck access to major roads, and document the local IT talent pool. Cloud site teams should score the surrounding district, not just the parcel.
The OU team gave communities a map of what operators have already favored. It did not hand out a guarantee.
FAQ: What Draws Data Centers to a Community?
What draws data centers to a community, per the OU study? Land-use diversity was the strongest factor. Proximity to electrical substations, access to major roads and concentrations of IT workers also helped explain siting.
How many data centers did the researchers examine? 212 U.S. data centers operated by 11 major technology companies, including Amazon, Microsoft, Google and Meta.
Who led the research? Kijin Seong, Ph.D., assistant professor at OU's Christopher C. Gibbs College of Architecture, co-authored it. The material reviewed does not name the other researchers.
Does the study say how much power or water a data center uses? No. Seong described water and fiber as basic needs in an interview, but the study reports no tested water, fiber, electricity, investment, jobs or tax figures.
Does land-use diversity mean data centers prefer busy city centers? Not necessarily. The finding describes the mix around a site; a facility can sit on a quiet parcel inside a mixed district.
Does the study prove substations or workers cause siting decisions? No. The factors helped explain where facilities were built — an association, not a causal claim.
Can a town without many IT workers still attract a data center? Possibly. Robinson said developers can import labor, though the OU findings suggest a thin talent pool raises costs even if it does not rule a town out.
When was the OU announcement published? November 20, 2026, updated November 22, 2026.
via shattered.io (Source)
More from Amara Osei
Show full bio
Staff writer covering money, funding and market shifts around hardware layer of artificial intelligence at Die Signal.
794 articles
Same lot
- OpenAI to rebrand data centers as ‘compute campuses’ amid policy push
- Microsoft reviews 1,300-acre Rockford site for possible 1.4 GW campus
- US hyperscale data centers rival Denmark’s CO₂ output
- Microsoft buys 37 acres in Licking County for about $6.65 million
- Patmos to Convert Former Alabama Walmart Into 50MW Data Center