North Carolina approves data center rate class with 15-year contracts
North Carolina's NCUC approved a Duke Energy rate class for 50MW+ data centers from January 1, mandating 15-year contracts above 100MW and 75% minimum billing on contracted demand.
- Read
- 2 min
- Words
- 458
- Segment
- AI Datacenter Infrastructure
- Operator
- Amara Osei
Spec summary
- NCUC approved Duke Energy's data center rate class, effective January 1.
- Operators above 100MW face mandatory 15-year contracts; billing floor is 75% of contracted demand.
- Residential rates rise 4.7% (Progress) and 4.8% (Carolinas) annually over two years on average.
- Attorney general Jeff Jackson proposed the rate class in September.
- North Carolina joins Ohio and Virginia in enforcing large-load data center rate classes.

Data center operators in North Carolina will pay for at least 75 percent of their contracted power demand whether or not they consume it, under a rate class the North Carolina Utilities Commission (NCUC) approved for Duke Energy, effective January 1.
The schedule applies to data centers with capacities above 50MW. Facilities exceeding 100MW must sign a mandatory 15-year minimum contract. Operators pay for 75 percent of contracted demand regardless of actual consumption.
The rules go further than billing thresholds. Operators must make upfront payments covering the estimated costs of direct grid interconnections, new transmission lines, and upstream power generation assets built to serve their demand.
A stranded generation charge allocates the risk and cost of building and maintaining those plants if a customer exits its contract early. The NCUC also included provisions for interim power curtailment during capacity shortages or grid stress events.
What does the ruling change for other customers?
The NCUC ordered Duke to track data center service costs and operations as a separate customer class to ensure transparency, isolating large-load economics from the broader rate base.
Duke Energy Progress customers face average annual increases of approximately 3.4 percent over two years, with residential customers at 4.7 percent. Duke Energy Carolinas customers face a 3.7 percent average over the same period, and 4.8 percent for residential.
Duke Energy Carolinas serves 2.3 million households and businesses in Central and Western North Carolina, including Charlotte, Durham, and the Triad. Duke Energy Progress serves about 1.6 million customers in Central and Eastern North Carolina and the Asheville region.
Kendal Bowman, Duke Energy's North Carolina president, said: "We listened to our customers and worked closely with stakeholders to find a more cost-effective way forward."
She added: "This outcome keeps affordability at the forefront while allowing us to make the investments needed to strengthen reliability and support North Carolina's continued growth. That balance is what we were working to achieve."
North Carolina attorney general Jeff Jackson proposed the new rate class in September.
How does this fit the wider US picture?
North Carolina becomes the latest state to enforce a dedicated rate class for large-load data centers, joining Ohio and Virginia, among others.
The state-level spread signals a shift: regulators are moving data center infrastructure costs onto the operators that drive them, with contract lengths, minimum-take obligations, and exit charges as the standard toolkit.
For operators above 100MW, North Carolina now carries one of the stricter frameworks — a 15-year commitment backed by stranded-cost exposure.
The takeaway in plain words: from January 1, big data centers in North Carolina pay for the grid they use, and for most of the power they promise to take.
via datacenterdynamics.com (Source)
More from Amara Osei
Show full bio
Staff writer covering money, funding and market shifts around hardware layer of artificial intelligence at Die Signal.
793 articles
Same lot
- Dominion Reports 54.9GW of Data Center Demand in Contracting
- One Hour Off the Grid Saves a Texas Data Center $33.4 Million
- PJM plan would cut data center grid connection time to 12 months
- Nebius inks 50MW lease with AIB Data Centers in South Carolina
- Israel caps new data centers at 200MW and demands grid guarantees