ABL launches Astella with 3.5MW Curitiba data center
ABL unit Astella opened a 3.5MW, 8,800 sqm data center in Curitiba after R$60m of 2025-26 investment, with a R$300m national network deployment plan due by 2028.
- Read
- 3 min
- Words
- 615
- Node
- 14nm
- Operator
- Grace Kim
Spec summary
- Initial capacity: 3.5MW at the downtown Curitiba facility.
- Site size: 8,800 sqm of floor space in a 16-story building.
- Reported investment: R$60 million (US$10.6 million) between 2025 and 2026.
- Follow-on target: R$300 million (US$53.2 million) by 2028.
- Network deadline: End-2028 connections to São Paulo and selected Northeast states.

By Grace Kim
A 3.5MW data center opened in downtown Curitiba, Paraná, as Brazilian technology group ABL launched its new unit Astella and set a national network target for the end of 2028.
The 16-story building provides 8,800 sqm (94,720 sq ft) of floor space. It marks Astella's market debut; Astella is a company within ABL Group, also known as Grupo ABL.
ABL Group purchased the building from Vivo, part of the Telefónica Group, in 2018. The property had served as Vivo's main data center in Paraná since the carrier acquired GVT.
ABL Group has reportedly invested R$60 million (US$10.6 million) in the operation between 2025 and 2026, covering power, cooling and cybersecurity. It plans to add R$300 million (US$53.2 million) from its own funds by 2028 and extend the operation into other states.
ABL Group president Agnaldo Lopes said the facility “marks the beginning of a project to create a national, decentralized network for cloud computing, artificial intelligence, and data sovereignty.” Data sovereignty means control over where data is stored and managed.
The group decided to “resume data center operations in 2025 to meet demand from AI companies,” Lopes told local press. Astella's first project will use the Curitiba facility as the origin for traffic routed toward regions with few data centers.
What does this change for Brazil's data center capacity?
Curitiba gains an initial 3.5MW site, and the network plan gives companies in regions with sparse data center coverage a potential connection path. The scale is set: R$60 million funds work through 2026, while a further R$300 million by 2028 supports network links and expansion into other states.
Network build-out
Astella's first project uses a star-shaped topology, meaning traffic from the Curitiba center will radiate to network connection points, or nodes, in areas with low data center concentration. By the end of 2028, the company aims to connect the network with strategic data exchange points (interconnection hubs) in São Paulo and some states in the Northeast.
The plan separates the first operating investment from the broader network program. The R$60 million committed for 2025 and 2026 covers site infrastructure, including power, cooling and cybersecurity. The later R$300 million target, to come from ABL's own funds, forms the financial basis for the 2028 connection program and planned expansion beyond Paraná.
Demand from artificial intelligence companies drove the decision to restart operations, while the proposed topology spreads capacity away from markets with the highest concentration of data centers. Delivery now rests on the additional capital target and the company's 2028 connection deadline.
ABL's operating history
ABL Group, founded in 2000, previously worked in the data center sector. Lopes, the group's founding partner and majority shareholder, said the company opened one of Paraná's first private cloud data centers in 2015.
Between 2014 and 2021, ABL also operated as a broadband internet service provider. Copel acquired that business and created the provider Ligga Telecom, then sold Ligga Telecom in February to Brasil Tecpar.
Astella now combines that operating history with a new corporate identity inside ABL Group. The immediate asset is physical: 3.5MW of initial capacity, 8,800 sqm of floor space and a downtown Curitiba address. The longer proposition is a distributed network linking that site to low-density regions and strategic exchange points across Brazil.
For companies in those regions, the practical change is access to a planned connection route rather than an announced national footprint. They would still wait for the network's 2028 target, state-level expansion and the R$300 million follow-on investment.
via datacenterdynamics.com (Source)
More from Grace Kim
Show full bio
Market editor covering regulation, policy and their impact on hardware layer of artificial intelligence at Die Signal.
665 articles
Same lot · LOT-362C
- DSG-352665nmVodafone-Backed JV Commits $1bn to Build Egypt's Largest Data Center
- DSG-464410nmAres Pushes Sabey Data Centers Investment Past $500 Million
- DSG-97667nmSubmer and BSNL Sign MoU for AI-Ready Data Centers Across India
- DSG-849110nmNTT Data nears $6.3bn deal for Anthropic data center in Osaka
- DSG-312265nmG42 signs MoUs to build AI factory infrastructure in Greece