South Korea's Lee: Speed Is 'Life and Death' in Global AI Race
President Lee Jae-myung toured SK's AI data center site in Ulsan on the 21st, calling speed 'life and death' and flagging a construction labor shortage as fab and data center buildouts compete for workers.
- Read
- 3 min
- Words
- 663
- Segment
- AI Datacenter Infrastructure
- Operator
- Marcus Bennett
Spec summary
- President Lee Jae-myung visited SK's AI data center construction site in Ulsan on the 21st.
- About 900 people are working at the Ulsan AI data center construction site.
- Lee said construction labor is 'in very short supply' for advanced facility projects.
- Lee likened AI infrastructure to the Gyeongbu Expressway's role in industrialization.
- Attendees included SK Telecom CEO Chung Jae-hun and Science and ICT Minister Bae Kyung-hoon.

South Korean President Lee Jae-myung declared speed a matter of survival in the global AI infrastructure race during a visit on the 21st to the construction site of SK's artificial intelligence data center in Ulsan. "Speed is a matter of life and death," Lee said. "Competing on speed is the key, not only for our own needs but for international competition."
The Ulsan stop follows a recent visit to Chungcheong, part of a tour of mega-project sites in the Yeongnam region. After a briefing on project progress, Lee framed the facility as a test case for broader ambitions. "I am hoping the successful execution of Ulsan's AI data center project will serve as a primer that draws additional investment from global AI companies," he said.
Why the president calls it an 'AI expressway'
Lee linked data centers directly to the semiconductor industry and to future demand from physical AI. "AI data centers are a major source of demand for semiconductors, and they are also core infrastructure that will underpin physical AI such as robots and self-driving vehicles," he said.
He reached for a historical analogy. "Just as the Gyeongbu Expressway once opened the way for South Korea's industrialization, I think an AI expressway will now open the way for the country's great AI transition."
The Gyeongbu Expressway, completed in 1970, connected Seoul to Busan and anchored the country's export-driven industrial buildout. Lee's argument is that compute infrastructure now plays the same structural role.
What does this change for regions outside Seoul?
Lee positioned Ulsan as proof that advanced infrastructure can grow outside the capital region, where most AI investment has clustered until now. "AI infrastructure investment had been taking place mainly in the capital region, but this time it is proceeding with a focus on the provinces," he said. "I think this will become an actual case proving that it is possible in the provinces as well, and that this can create new growth momentum."
He went further on the policy stakes: "All sorts of problems are arising in South Korea because of concentration in the capital region. We have to create new opportunities in the provinces and also resolve the national task of balanced development, and mega-projects will be an important and central mechanism for that."
A labor bottleneck in construction
The visit also surfaced a practical constraint: construction labor. Roughly 900 people currently work on the Ulsan site, according to figures Lee said he received. "From the reports I receive overall, they say labor is in very short supply for these advanced facility projects," he said.
The shortage stems from parallel buildouts of semiconductor fabs and AI data centers. "We still have to keep building semiconductor fabs, but labor is already in considerable shortage, and if data center construction expands further, the construction labor issue will not be simple," Lee said. "I will have the government ministries give a lot of thought to how we are going to prepare that workforce."
Wearing a white hard hat during the site tour, Lee pressed officials on staffing. He asked questions including "Aren't you short of construction workers?" and "You need specialized workers, don't you?"
Permits and approvals moved fast
Lee credited the local government with accelerating the project. "The local government in particular has been playing a large role on permits and approvals and the like," he said. "It seems to have helped a great deal in picking up the pace."
The visit drew a senior delegation:
- SK Telecom (017670) CEO Chung Jae-hun
- SK Hyper CEO Chung Suk-keun
- Science and ICT Minister Bae Kyung-hoon
- Ulsan Mayor Kim Sang-wook
- Presidential chief of staff Lim Kwang-hyun
- National strategic investment adviser Lee Won-joo
- Senior presidential secretary for AI future planning Lee Hae-min
The presence of two presidential AI policy officials signals that the Ulsan project sits inside a national strategy rather than a single corporate build.
via en.sedaily.com (Source)
More from Marcus Bennett
Show full bio
News editor covering regulation, policy and their impact on hardware layer of artificial intelligence at Die Signal.
752 articles
Same lot
- South Korea's Lee Tours Ulsan AI Data Centre: 'Speed Is Vital'
- SK's Ulsan AI Data Center 71% Complete as Lee Ties Cheap Power to Competitiveness
- Mobilint Targets Korea's Edge AI Market With NPU Push
- Ulsan Ranks First in Smart Factories, Last in Local AI Supply
- Chungcheong Investment to Rise $16 Billion With 112 Companies