Test report DSG-1080 · Rev C · tested November 17, 2026

AI Datacenter InfrastructureDevice under test

Milan set to pass Dublin as Europe's fifth-largest data center market

CBRE expects Milan to pass Dublin as fifth-largest by 2028 on 255MW of hyperscaler capacity, while European colocation take-up reaches 1.34GW and year-end vacancy falls to 10.3%.

Read
3 min
Words
586
Node
5nm
Operator
Marcus Bennett

Spec summary

  1. Milan is forecast to become Europe's fifth-largest data center market by 2028, with 255MW of new capacity.
  2. CBRE says the 255MW of new capacity is exclusively for hyperscalers, mostly in west Milan.
  3. Milan and Dublin are separated by 100MW of operational capacity.
  4. Italy's data center market has grown sixfold since 2020.
  5. European colocation take-up reached 1.34GW against 1.26GW of new supply; vacancy is forecast at 10.3%.
CBRE: Milan set to overtake Dublin as fifth-largest data center market in Europe by 2028
Fig. ACBRE: Milan set to overtake Dublin as fifth-largest data center market in Europe by 2028 — rperucho / pixabay

Marcus Bennett

Milan is forecast to become Europe's fifth-largest data center market by 2028, supported by 255MW of new capacity, all earmarked for hyperscalers according to CBRE. Most of that capacity will sit in west Milan.

Meeting this forecast would put Milan ahead of Dublin, which currently holds fifth place. The two cities are separated by 100MW of operational capacity.

What drives Milan's rise?

CBRE, the real estate services firm, says in its Q3 2026 European Data Centers report that the new capacity will support the cloud regions hyperscalers have announced. It also records Milan's highest take-up among the firm's ten tracked secondary markets.

The ten tracked secondary markets are:

  • Milan
  • Berlin, Brussels, Madrid and Munich
  • Oslo, Stockholm, Warsaw, Vienna and Zurich

CBRE said Milan's demand reflects broader interest in non-core markets, driven by power availability and price.

Andrew Jay, CBRE's head of Data Centre Solutions for Europe, said:

“Milan’s accelerated development trajectory highlights the city’s transition from a secondary market into a top European data centre hub. This evolution reflects a broader geographic diversification of data centre activity, with Southern Europe growing in relevance when compared to traditional data centre clusters, namely Frankfurt, London, Amsterdam, Paris, and Dublin (FLAPD).”

CBRE groups Frankfurt, London, Amsterdam, Paris and Dublin as the traditional FLAPD cluster.

What does the forecast change for operators?

For hyperscalers, the 255MW pipeline adds a western Milan option tied to their announced cloud regions, lifting Southern Europe's importance relative to traditional clusters.

For operators outside hyperscaler demand, the near-term benefit is indirect, so buyers must weigh Milan's power availability and price against Dublin's grid restrictions and the court challenge to them.

The Milan forecast does not directly change Europe's colocation balance because hyperscalers account for all of the planned capacity.

Power rules reshape Dublin

Italy's data center market has grown sixfold since 2020, CBRE said. Dublin's supply growth has declined since the introduction of rules that acted as an effective ban on new data center grid connections.

Late last year, Ireland lifted the de facto ban and imposed new grid-connection conditions for every operator seeking to connect a data center to the grid. Operators seeking a connection must:

  • install on-site generation and battery systems capable of meeting the facility's full electricity demand.
  • provide excess power back to the grid when necessary.

Several environmental groups are challenging Ireland's new rules in the High Court.

Despite the dispute, Dublin recorded more Q3 take-up than any other core market. A hyperscaler moved into vacant space on one campus. CBRE called the move “unusual” because operators remain cautious about investing in Dublin.

European colocation supply tightens

CBRE expects European data center vacancy to fall to 10.3% by year-end, compared with 12.3% the previous year.

European colocation take-up reached 1.34GW against 1.26GW of new supply, the first time in Europe that demand for completed colocation capacity exceeded supply.

CBRE attributed the result to AI infrastructure demand from neoclouds and hyperscalers.

London, Paris and Dublin accounted for more than half of Europe's Q3 take-up. That reversed the previous quarter, when the majority of take-up occurred in continental European markets.

Two separate markets stand out. Milan's 255MW pipeline is hyperscaler-led and geographically concentrated. Europe's colocation market is absorbing capacity faster than developers deliver it. Power access, price and local grid rules remain central to location decisions.

via datacenterdynamics.com (Source)

Filed under

  • data-centers
  • hyperscalers
  • colocation
  • power-availability
  • grid-connections
Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

News editor covering regulation, policy and their impact on hardware layer of artificial intelligence at Die Signal.

681 articles

Same lot · LOT-362D

« Previous articleNext article »