Google Halts Belgian Data Center Build Over Missing Permit

Google has halted work on a data center near Charleroi after Wallonia alleged building without a permit; Greenpeace launched expedited proceedings after drone footage showed progress.

Read
2 min
Words
481
Segment
AI Datacenter Infrastructure
Operator
Marcus Bennett

Spec summary

  1. Google stopped construction of a data center near Charleroi, Belgium, after authorities alleged a "serious offence" — no valid permit.
  2. Greenpeace initiated expedited proceedings on Wednesday after November drone footage showed major construction progress without approval.
  3. Google obtained a permit in 2024, but later applied for a larger footprint and Sambre river water cooling, replacing the original air cooling.
  4. In October, Finnish authorities ordered work stopped at two Google data center sites pending environmental impact assessments.
Behörde sieht "schwere Straftat": Google muss Bau von Rechenzentrum in Belgien stoppen
Behörde sieht "schwere Straftat": Google muss Bau von Rechenzentrum in Belgien stoppen — 652234 / pixabay

Google has stopped construction of a data center in southern Belgium after regional authorities accused the company of a "serious offence" — building without a valid permit.

A Google spokesperson told AFP on Saturday: "We have stopped work in line with the instructions of the local authorities and until we receive further notice." The company added: "We have been active in Belgium for over 15 years and remain committed to complying with local laws."

The site sits in a business park on former mining land near Charleroi, in the Walloon region. Wallonia's regional authorities said no proper building permit exists for the current project. The allegations came to light through aerial surveillance.

How did the conflict start?

Greenpeace announced on Wednesday that it had initiated expedited legal proceedings. Drone footage taken in November showed construction had advanced considerably despite the absence of a permit. The environmental group acted after the images contradicted the legal status of the works.

The dispute traces back to a change in the project's design. Google received a permit for the data center in 2024. This year, the company applied for two substantial modifications:

  • a larger building footprint
  • a permit to draw cooling water from the nearby Sambre river

The original application specified air cooling. The switch to river-water cooling and the expanded footprint triggered a fresh permitting process that had not concluded when construction continued.

What does this change for Google's European buildout?

The stop order in Wallonia is the second such interruption in Europe within months. In October, Finnish authorities ordered work to halt at two Google data center sites until the required environmental impact assessments are complete. Taken together, the two cases show regulators and NGOs increasingly willing to stall large hyperscale projects on procedural grounds.

The Belgian case also highlights a recurring friction point: cooling water. Data centers that shift from air to water cooling materially change their environmental footprint, and permitting regimes treat that as a new approval rather than an amendment, which can strand builders mid-construction when applications are filed late.

For Google, the immediate cost is delay, not cancellation. The Charleroi project remains live, and the company can pursue the outstanding permits for the larger footprint and river-water cooling. But work on the ground stays frozen until authorities give clearance, and the Greenpeace expedited proceeding adds a second track of legal risk on top of the administrative one.

What happens next?

Google says it will await further instructions from local authorities. The pending decisions include the expanded site permit and the water-use approval from the Sambre. The Greenpeace fast-track proceeding will run separately.

The episode fits a broader pattern across Europe, where data center construction now faces denser scrutiny from environmental groups and regional regulators alike — and where the technical switch from air to water cooling has become a flashpoint in permitting disputes.

via n-tv.de/rss (Source)

Filed under

Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

News editor covering regulation, policy and their impact on hardware layer of artificial intelligence at Die Signal.

799 articles

Same lot

« Previous article