Core Scientific to quit Bitcoin mining by end of 2026

Core Scientific will exit Bitcoin mining by year-end 2026 as colocation hits 92.5% of Q3 revenue at $215.4M, with 485MW billed and 1,120MW contracted.

Read
3 min
Words
612
Node
45nm
Operator
Amara Osei

Spec summary

  1. Core Scientific expects to complete its exit from Bitcoin mining by the end of 2026, entering 2027 as a colocation-only provider.
  2. Colocation generated $215.4 million of $232.9 million Q3 revenue, about 92.5% of the total.
  3. The company sold 3,374 Bitcoin for $286.8 million in the first nine months of 2026 and held 32 Bitcoin at end-September.
  4. CoreWeave has 590MW contracted across five campuses; the AMD partnership covers 530MW due for completion by end-2028.
  5. Q3 capital expenditure totalled $985.1 million; the company ended September with $803.9 million in cash.
Core Scientific to exit Bitcoin mining by end of 2026 as it grows AI colo business
Fig. ACore Scientific to exit Bitcoin mining by end of 2026 as it grows AI colo business — Tho-Ge / pixabay

Core Scientific expects to exit Bitcoin mining entirely by the end of 2026 and enter 2027 operating solely as a high-density colocation provider for AI workloads. CEO Adam Sullivan confirmed the timeline on November 5 during the company's third-quarter earnings call: "We expect to complete our exit from bitcoin mining by year-end."

The pivot is already measurable. Colocation generated $215.4 million of the company's $232.9 million total revenue in Q3 — roughly 92.5 percent of the quarter — up from $15 million in Q3 2025. Total revenue nearly tripled from $81.1 million a year earlier. Adjusted EBITDA reached $133.6 million, compared with $41.1 million in Q2 2026 and $6.5 million in Q3 2025. Core Scientific reported net income of $1.18 billion, against a $144 million loss a year earlier, driven primarily by a non-cash gain from the revaluation of warrants.

How fast is the mining business shrinking?

Chief financial officer Jim Nygaard said the company had nearly 50 percent fewer miners online at the end of September than at the end of 2025. Revenue figures show the same trajectory:

  • Self-mining revenue fell to $12.3 million in Q3, from $57.4 million a year earlier.
  • Third-party miner hosting revenue declined to $5.2 million, from $8.7 million.
  • The two mining businesses together produced $17.4 million, down from $66.2 million in Q3 2025.

Core Scientific sold 3,374 Bitcoin for $286.8 million during the first nine months of 2026 to fund capital expenditure and other cash requirements. It held 32 Bitcoin, worth $2.7 million, at the end of September — down from 2,537 Bitcoin at the end of 2025. In short: the treasury and the machines are both nearly gone.

What is being sold off?

The company's 10-Q filing lists mining, electrical and high-performance computing (HPC) equipment as held for sale during Q3. Core Scientific had initially earmarked only mining and electrical equipment for disposal in Q2, then widened the scope. Some assets were sold during the current quarter. The remaining held-for-sale equipment carried a value of $29.7 million at September 30, and the company expects to complete the sales within one year of the assets' initial classification. The wind-down of mining operations is scheduled to finish in Q4.

How much AI capacity is contracted?

The company billed for 485MW of colocation capacity at the end of September, up from 395MW at the end of June. Its contracted pipeline runs through two counterparties:

  • CoreWeave: 590MW contracted across five campuses, with full delivery expected in early 2027.
  • AMD partnership: 530MW contracted, comprising direct AMD leases and leases with an AMD-backed neocloud. Initial deliveries are expected in the first half of 2027, with the full programme due for completion by the end of 2028.

The AMD capacity spans Pecos and Hunt County in Texas; Dalton, Georgia; Muskogee, Oklahoma; and Auburn, Alabama.

What is being built?

In August, Core Scientific completed its acquisition of Polaris DS for approximately $444 million. The deal added a former cryptomining site adjacent to its Muskogee campus, bringing roughly 40 acres and 440MW of grid-connected power capacity. The acquisition is part of plans to expand the Muskogee campus to 1.5GW of gross power.

Capital expenditure, including land and development rights acquisitions, totalled $985.1 million for the quarter. The company ended September with $803.9 million in cash and cash equivalents — enough liquidity, on paper, to keep the build-out funded while Bitcoin leaves the balance sheet.

By this time next year, Core Scientific will be a colocation operator and nothing else.

via datacenterdynamics.com (Source)

Filed under

  • core-scientific
  • bitcoin-mining
  • ai-colocation
  • coreweave
  • amd
Share this article:

More from Amara Osei

Amara Osei

Show full bio

Staff writer covering money, funding and market shifts around hardware layer of artificial intelligence at Die Signal.

698 articles

Same lot · LOT-362C

« Previous articleNext article »