  1. Centrus held $2.236 billion cash at end-September with a $7 billion order book extending to 2040.
  2. Oklo prepayed $35 million against HALEU enrichment services in 2029-2031 under a take-or-pay contract signed 11 November.
  3. DOE awarded a $900 million contract for commercial HALEU capacity at Piketon, requiring one tonne by July 2032.
  4. Q3 revenue fell to $55.5 million from $74.9 million; adjusted net loss was $9.4 million.
  5. LEU stock is down about 75.3% from its January high of $345.60, trading near $85.43.
Centrus: A New Investment Story in Nuclear Energy
Centrus: A New Investment Story in Nuclear Energy — Petr / unsplash

Centrus Energy closed September with $2.236 billion in cash and equivalents and a $7 billion order book running to 2040 — paired with a $10.6 million gross loss in Q3. The gap between those two numbers is the whole story. The nuclear fuel supplier (ticker LEU on the NYSE) is collecting cash and signing contracts now, but its new production capacity only starts delivering near the end of the decade.

What does the money actually fund?

Centrus is rebuilding US enriched uranium production, and the funding is arriving from three directions.

  • Oklo. On 11 November Centrus and Oklo signed a final HALEU (high-assay low-enriched uranium) supply agreement covering enrichment services in 2029-2031 on take-or-pay terms. Oklo committed two prepayments totaling $35 million, credited against future fuel purchases. The deal was announced on 12 November.
  • Meta, indirectly. A 30 September agreement ties into Oklo's energy project for Meta in Ohio. On 2 November the first Meta tranche was released from escrow and paid directly to Centrus against future fuel orders. Oklo's campus targets 1.2 GW to power Meta data centers.
  • Washington. American Centrifuge Operating, a Centrus unit, received a $900 million Department of Energy contract to build commercial HALEU capacity at Piketon, Ohio, paid on production milestones. It requires one tonne of HALEU by July 2032, plus two options of five tonnes each. Separately, the October Westerman acquisition — $95 million cash, $21 million stock, $116 million total — pulled equipment manufacturing in-house.

Centrus plans more than $560 million of investment in its Tennessee facilities. It completed the first new centrifuge and began shipping equipment from Oak Ridge to Ohio ahead of its annual target. First new centrifuges should run in Ohio in 2029.

Is the $7 billion order book solid?

Partly. As of 30 September, $6.2 billion of the backlog sits in the LEU (low-enriched uranium) segment. About $5.4 billion represents conditional LEU and HALEU sales, with $5.1 billion under final agreements — all contingent on building and commissioning new capacity on schedule.

There's a sharper catch. About $800 million of the Technical Solutions backlog is tied to the current HALEU cascade operation contract, and the proposed DOE FY2027 budget omits further funding for it. DOE also says it doesn't plan to exercise additional options. This is separate from the new $900 million commercial HALEU expansion order.

What about the balance sheet?

In September the company raised roughly $500 million gross through an equity and warrant offering. Additional warrants could theoretically add about $2 billion, but strikes sit at $227-363 per share — with the stock around $85, that's not a funding source to count on.

Market capitalization stands near $1.76 billion, which makes the cash pile look outsized. It isn't, quite: convertible notes carry a book value of about $1.18 billion. Cap the comparison there.

Q3 was weak on operations. Revenue fell to $55.5 million from $74.9 million a year earlier. Adjusted net loss hit $9.4 million. GAAP net income of $31.6 million came mostly from a $46.4 million non-cash warrant liability revaluation plus higher investment income. Nine-month capex reached $226.4 million; 2026 guidance holds at $450-500 million revenue with $350-500 million total capex, excluding Westerman.

Where the stock trades

LEU has lost about 75.3% from its January high of $345.60, now at $85.43. The November candle — open $104.74, high $118.29, low $75.91 — is unfinished, down 17.29% month-to-date. The densest support sits at $60-63, where the 61.8% Fibonacci retracement ($60.92), the 100-month moving average ($62.97) and diagonal support converge. Buyers' first task is holding $75.91 and reclaiming $100-105; resistance follows at $118-120, then the $176-200 supply zone.

What could break the plan?

Two dates matter. The Piketon facility lease expires 1 October 2027; DOE has said it will work on a long-term extension until 31 December 2026 but isn't obligated to sign. Supply timing is the second constraint: Centrus purchase obligations under the TENEX contract may run to 2028, and the Russian decree requiring per-shipment export licenses stays in effect through end-2027. The Orano agreement covers supplies through 2030. The company must bridge to its own output without defaulting on any of it.

Centrus holds its Investor Day on 7 December at Piketon, with expansion timelines, capex, Westerman integration and lease terms on the agenda. The resources and agreements exist. Deliveries, capacity and cash flow are what the market will price — not announcements.

via tradingview.com (Source)

Filed under

Share this article:

More from Grace Kim

Grace Kim

Show full bio

Market editor covering regulation, policy and their impact on hardware layer of artificial intelligence at Die Signal.

791 articles

Same lot

« Previous articleNext article »